The work is resumed from the fastening of the transverse lag, placing them every 75 cm and attaching them to the beams with galvanized screws 15 cm long. To do this, in the beams and lags, the holes for the bolts are pre -drilled. To “drown” the heads of the bolts, the holes in the lags are unscrewed by the Forester drill with a diameter of 30 mm or cylindrical zenkovka.
The flooring of the floor with boards with boards 14, 5 cm start with a base of the house with an indent of 2 cm from the masonry. A gap of 5 mm is left between the boards using wooden gaskets. Boards are attached to the lags of galvanized screws with a complete cut. The racks of the fence are screwed to the transverse lags, having previously drilled in their upper part of the hole to pull the cable as handrails. Where the fastening should be more durable, metal linings are additionally used. Synthetic rope is attached with bolts.
The time for the construction of the terraces will be approximately 2, 5 working days if two experienced craftsmen will work. Terrace Square- 18 m2 (6×3 m).